NAVFAC Design-Build Model Request for Proposal - Marine Corps BEQ

1.0 Table of Contents (RFP Parts 2-6)

1.  PART 2 – GENERAL REQUIREMENTS

01 14 00          WORK RESTRICTIONS
01 20 00          PRICE AND PAYMENT PROCEDURES
01 30 00          ADMINISTRATIVE REQUIREMENTS
01 31 19.05 20  CONCEPT DESIGN WORKSHOP
01 31 23.13 20  ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM (eCMS)
01 32 17.00 20  COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00.05 20  CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20  DESIGN SUBMITTAL PROCEDURES
01 33 29          SUSTAINABILITY REQUIREMENTS AND REPORTING
01 35 13          SPECIAL PROJECT PROCEDURES
01 35 26          GOVERNMENTAL SAFETY REQUIREMENTS
[01 42 15          METRIC MEASUREMENTS]
01 45 00          QUALITY CONTROL
01 45 35          SPECIAL INSPECTIONS
01 50 00          TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19          TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19          CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00          CLOSEOUT SUBMITTALS
[01 78 23          OPERATION AND MAINTENANCE DATA]
[01 78 24.00 20  FACILITY DATA WORKBOOK (FDW)]

[01 91 00.15 BUILDING COMMISSIONING]
[01 91 19   BUILDING ENCLOSURE COMMISSIONING]

 

 

2.  PART 3 – PROJECT PROGRAM

CHAPTER 1 & 2.  PROJECT DESCRIPTION AND PROJECT OBJECTIVES
CHAPTER 3.  SITE ANALYSIS
CHAPTER 4.  SPACE TABULATION FORM
CHAPTER 5.  ROOM REQUIREMENTS
CHAPTER 6.  ENGINEERING SYSTEMS REQUIREMENTS

3.  PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS

A10 FOUNDATIONS
A20 BASEMENT CONSTRUCTION
B10 SUPERSTRUCTURE
B20 EXTERIOR ENCLOSURE
B30 ROOFING
C10 INTERIOR CONSTRUCTION
C20 STAIRS
C30 INTERIOR FINISHES
D10 CONVEYING
D20 PLUMBING
D30 HVAC
D40 FIRE PROTECTION
D50 ELECTRICAL
E10 EQUIPMENT
E20 FURNISHINGS
F10 SPECIAL CONSTRUCTION
F20 SELECT BLDG DEMOLITION
G10 SITE PREPARATIONS
G20 SITE IMPROVEMENTS
G30 SITE CIVIL/MECHANICAL UTILITIES
G40 SITE ELECTRICAL UTILITIES
Z10 GENERAL PERFORMANCE TECHNICAL SPECIFICATION

4.  PART 5 – PRESCRIPTIVE SPECIFICATIONS

[-- Not used --]

5.  PART 6 – ATTACHMENTS

FORMS
DRAWINGS
REPORTS
APPLICABLE UFC OR FC