NAVFAC Design-Build Model Request for Proposal - Armory
C20 STAIRS
NAVFAC PTS-C20 (September 2022)
------------------------------
Preparing Activity: NAVFAC SUPERSEDING PTS-C20 (December 2018)
PERFORMANCE TECHNICAL SPECIFICATION
SECTION C20
STAIRS
09/22
NOTE: This section is intended to be used as a guide and contains requirements that are common to many different types of facilities. In addition, there may be special requirements for a particular project that are not addressed at all. The RFP preparer will need to incorporate additional information to address these special requirements in this PTS and corresponding Part 3 ESR. If the RFP Preparer chooses to delete building elements that are not required for the project, do not change the remaining Uniformat paragraph designations (example A102001). Uniformat designations are unique to the products they are assigned to. However, the subparagraphs numerical extension (example - 1.2 or a,b,c of the Uniformat designations may change if subparagraphs are deleted).
This guide specification is formatted utilizing Uniformat II, an industry recognized standard, ASTM E 1557. When the RFP preparer chooses to add a paragraph that does not apply to an existing building element already included in the specification, refer to the Uniformat/WBS located on the NAVFAC Design-Build Website for a listing of Uniformat II designations and definitions.
NOTE: The RFP preparer may view or hide the criteria notes in this PTS section by modifying the WORD preferences for "Hidden text". To view the criteria notes, choose "File" then "Option". Click "Display" then check the "Hidden text" box under "Always show these formatting marks on the screen". In the same section, check the box for "Print hidden text" under "Printing options" to print the criteria notes.
NOTE: The following Table of Contents is for navigation purposes within the document and is not intended to be part of the final edited documents
TABLE OF CONTENTS
C20 GENERAL
C20 1.1 DESIGN GUIDANCE
C20 1.2 PERFORMANCE VERIFICATION AND ACCEPTANCE TESTING
C20 1.3 DESIGN SUBMITTALS
C20 1.4 CONSTRUCTION SUBMITTALS
C2010 STAIR CONSTRUCTION
C201001 INTERIOR AND EXTERIOR STAIRS
C201001 1.1 STEEL STAIRS
C201001 1.2 ALUMINUM ALLOY PRODUCTS
C201001 1.3 FINISHES
C201001 1.4 CONCRETE STAIRS / STEPS
C201001 1.5 WOOD STAIRS
C201002 FIRE ESCAPE STAIRS
C201090 STAIR HANDRAILS, GUARDRAILS, AND ACCESSORIES
C201090 1.1 HANDRAILS
C201090 1.2 METAL LADDERS
C20 GENERAL
RFP Part 3 including the Engineering System Requirements (ESR) provide project specific requirements. The RFP Part 4, Performance Technical Sections (PTS) provide generalized technical requirements that apply to multiple facility types and include more requirements than are applicable to any one project. Therefore, only the RFP Part 4 requirements that apply to the project and further define the RFP Part 3 project specific requirements are required.